Contract law in the UAE: when a contract binds, and what happens on a breach
Since 1 June 2026, contracts in the UAE are governed by the Civil Transactions Law, Federal Decree-Law No. 25 of 2025, which replaced the 1985 law. A contract is the law of the parties: neither side can withdraw from it or change it except by agreement, a court judgment or the law, and it must be performed in good faith (Articles 113, 221 and 232). When one side breaks it, the other can, after a formal notice, ask the court to order performance or to end the contract, and claim compensation (Articles 234, 336 and 337).
On this page
Not covered in this guide:
- Contracts made before 1 June 2026, which the new law does not cover unless it says so (Article 4(1)).
- Employment, tenancy and other contracts with their own laws, which prevail where they differ (Article 4(3)).
When a contract binds
A contract is formed when an offer and an acceptance meet. It becomes the law of the parties, and it cannot be undone or changed except by agreement or for reasons the law sets (Federal Decree-Law No. 25 of 2025, Article 113). It needs (Article 124):
- agreement on the essential elements
- a subject that exists or can exist, is identified or can be identified, and may lawfully be dealt in
- a lawful cause
Verbal and written contracts
- Most contracts are formed by consent given in any way: words, writing, a customary sign, or conduct that leaves no doubt (Articles 117(1) and 126).
- Some contracts must take the form the law requires for them (Article 117(2)).
- An acceptance that adds to or changes the offer is a rejection and a new offer (Article 125(4)).
- Silence is not acceptance, unless agreed, where the parties have dealt before and the offer relates to that dealing, or where the offer is purely for the other side's benefit (Article 128).
- Goods or services displayed with a price are an offer. Advertising and price lists are, in case of doubt, an invitation to make one (Article 127).
Good faith, disclosure and how a contract is read
- A contract must be performed as written and in good faith, and it includes what the law and custom attach to it (Article 221).
- Negotiations must be conducted and broken off in good faith. Negotiating does not oblige anyone to sign, but a party who negotiates or walks away in bad faith pays the actual damage caused, not the gains expected from the contract, unless agreed otherwise (Article 121).
- Each side must disclose information that is decisive to the other's consent. This duty cannot be excluded, and the harmed party can ask for the contract to be annulled (Article 122).
- Using or disclosing confidential information obtained in negotiations without permission brings liability (Article 123).
- Clear wording is applied as it stands. Where interpretation is needed, the court looks for the parties' common intention, and doubt is read in favour of the party who carries the obligation or the weaker party (Articles 119 and 120).
Standard-form contracts and unfair terms
A standard-form contract is one whose general terms are set in advance by one side and cannot be negotiated (Article 118(2)). The law protects the side that signs it:
- If it contains abusive terms, the court may amend them or release the weaker party from them, and any agreement to the contrary is void (Article 223).
- Ambiguous wording in it may not be read against the weaker party (Article 120(2)).
- Terms added to a standard form prevail over the printed terms, even if those were not struck out (Article 221(3)).
Breach of contract: your options
| Option | What the law says | Article |
|---|---|---|
| Withhold your own side | In a contract with obligations on both sides, either party may refuse to perform while the other does not perform what is due | 222 |
| Performance | After notice, the court can order the other side to perform where possible; it can limit an onerous performance to money if that causes the creditor no serious harm | 234, 331 |
| Ending the contract | After notice, the court can rescind it, give the other side time, or refuse if what is missing is minor | 234 |
| Compensation | For non-performance, delay, or partial or defective performance, unless an outside cause made it impossible | 336 |
- Compensation is due only after a formal notice, unless the law or the contract says otherwise. No notice is needed, for example, where the other side has said in writing that it will not perform (Articles 337 and 338).
- A clause that ends the contract automatically on a breach still needs notice, unless the contract expressly waives it (Article 235).
- Where neither the law nor the contract fixes the amount, the court awards the damage actually suffered (Article 339).
- A contract can fix compensation in advance. The court can reduce it if it is excessive or the obligation was partly performed, and the creditor can claim more only by proving fraud or gross fault (Article 340).
How to file a civil case in Dubai: notice, fees and the steps
Hardship and force majeure
- Hardship: if exceptional, general events that could not be foreseen make performance so onerous that it threatens the debtor with grave loss, the court may, after weighing both sides, reduce the obligation to a reasonable level or rescind the contract. An agreement excluding this is void (Article 224).
- Force majeure: if it makes performance impossible, the matching obligations end and the contract is dissolved by itself. If only part becomes impossible, or the impossibility is temporary in a continuing contract, either side can rely on it or ask the court to end the contract (Article 236).
- When a contract is dissolved, the parties are put back where they were before it; if that is impossible, the court awards compensation (Article 237). Each side may hold what it received until the other returns what it took (Article 238).
Ending a contract by agreement, and time limits
- The parties can agree to cancel the contract after it is made, in whole or in part (Article 233).
- Otherwise, a valid binding contract cannot be withdrawn from, changed or rescinded except by agreement, a court judgment or the law (Article 232).
- A claim is not heard after 15 years if the other side denies it, unless the law sets another period (Article 429). Some claims have shorter periods; the civil case guide lists them.
Questions about contract law in the UAE
Which law governs contracts in the UAE?
The Civil Transactions Law, Federal Decree-Law No. 25 of 2025, in force since 1 June 2026. It replaced the 1985 law, which still matters for contracts made before that date (issuing decree, Articles 2 and 3; the law, Article 4(1)).
What happens if someone breaks a contract in the UAE?
After a formal notice, the other side can ask the court to order performance or to end the contract, and claim compensation for the damage actually suffered or the amount the contract fixes (Articles 234, 337, 339 and 340).
Is a verbal contract valid in the UAE?
Most contracts are formed by consent given in any way, including words or conduct, unless the law requires a particular form for that kind of contract (Articles 117 and 126).
Can a court reduce a penalty clause?
Yes. The court can reduce agreed compensation if the debtor proves it is excessive, the obligation was partly performed, or the creditor's own fault contributed. A clause excluding this is void (Article 340).
Can I cancel a contract because circumstances changed?
Only through the court, and only where exceptional, general and unforeseeable events make performance so onerous that it threatens grave loss. The court may then reduce the obligation or rescind the contract (Article 224).
Sources and review
Every statement was checked against the official texts on 27 November 2026 and reviewed by AK Advocates & Legal Consultants, a Dubai law firm (licence ADF-2014-327 from the Dubai Legal Affairs Department). Where the English and Arabic texts differ, the Arabic text prevails.
We check this guide again whenever the Civil Transactions Law is amended.
General information, not legal advice. Reading this or contacting us does not by itself create a lawyer–client relationship.
Related
- Civil lawyers in DubaiContract disputes, unpaid debts, bounced cheques and compensation claims.
- How to file a civil case in DubaiNotice, conciliation, fees and the steps in court.
- Payment orders in the UAEA faster route for a written, fixed debt.
- Partner and shareholder disputesDisputes inside an LLC, and the law that settles them.
Can we help?
Tell us the type of matter and how to reach you. Please don't send documents or private details yet.
Your request goes to the firm's legal team in Business Bay.
Get directions
- Mon to Thu
- 9:00 to 18:00
- Fri
- 9:00 to 15:00
- Sat
- Closed
- Sun
- 10:00 to 18:00
Licensed by the Dubai Legal Affairs Department, licence ADF-2014-327
AK Advocates